A microgrid that cannot be permitted is a drawing.

Generators, batteries, solar and bidirectional chargers each carry their own permit and, where they can export power, their own agreement with the utility. County Line files all of it, with the one-line diagram the inspector and the utility both read.

Talk through the house

Goes to the County Line office. The office calls you back. Privacy.

On paper first

Three authorities, one drawing.

A residential microgrid answers to three authorities, and the design has to satisfy all of them before the first conduit is set. The building department of the city or county issues the electrical permit and sends the inspector; in County Line's area that is a different office for Thousand Oaks, Westlake Village, Calabasas, Hidden Hills, the City of Malibu, the City of Los Angeles for the Palisades, Brentwood and Bel Air, and the unincorporated parts of Los Angeles, Ventura and Santa Barbara counties, each with its own submittal habits. The gas utility or the propane supplier governs the fuel connection, which is plumbing work by a licensed contractor. And the electric utility, Southern California Edison or LADWP, governs anything that can push power toward the grid.

That last one is the piece homeowners rarely expect. A standby generator behind a transfer switch never exports, so the utility is not involved beyond the permit. A battery, a solar array and a bidirectional EV charger can all export, and in Edison territory they are interconnected under Rule 21, with an application, equipment that meets the listing requirements, and the utility's permission to operate before the system is switched on. LADWP has its own equivalent. The paperwork names every piece of equipment and its settings, which is one more reason a residential microgrid designed by one contractor as one system is easier to approve than five installations that each described a different house.

The one-line diagram is the document everyone reads. It shows the service entrance, the meter, the main disconnect, the transfer device or gateway, the generator, the battery inverter, the solar inverter, the EV gateway, the smart panel or critical-loads subpanel, and every conductor between them with its size and protection. The inspector uses it to check the installation; the utility uses it to see where the island forms and what can export; the next electrician, in fifteen years, uses it to understand what was built. County Line produces it before equipment is ordered and leaves it on the wall of the electrical room when the job is done.

Inspections come in layers. A rough inspection where conduit and boxes are visible on new construction; a final where the equipment is set, labeled and tested; sometimes a separate fire department sign-off for a propane tank or a battery system above a certain size, under the fire code's rules for energy storage. Labels matter more than people expect: a house with multiple sources has to tell a firefighter or a lineman, at the service, that there is a generator, a battery and solar, and where each disconnect is. The inspector checks the labels, and so does County Line before calling for the inspection.

None of this is a reason to skip the permit, and a system installed without one is a system an insurer and a buyer will both ask about. It is a reason to have the contractor who designed the system be the one who files, because the application and the drawing are the design, and the inspection is the first real test of whether the island forms the way the drawing says it does.

Back to the overview: Residential Microgrid.

Recessed downlights
Image courtesy of Lutron.

Questions

Does a home battery need a permit in California?

Yes. A stationary battery system requires an electrical permit and inspection with the local building department, may require a fire department review depending on size and location, and where it can export power, an interconnection agreement with the electric utility, which in Edison territory is Rule 21. County Line files all of these.

Who handles the utility interconnection?

County Line Electric handles the utility interconnection. It prepares and submits the application for batteries, solar and bidirectional EV equipment as part of the residential microgrid design, with the one-line diagram and equipment list the utility requires, and does not energize export-capable equipment until the utility's permission to operate is in hand.

Official references

Where the facts on this page come from.

County Line links to the authorities rather than restating them. Rules change; these pages are current.

Next step

Tell us what has to stay on.

Tell us what has to stay on when the grid is off: the well, the gate, the kitchen, the chargers, with your name, phone and city. Jeff walks the panel and the yard, then the design conversation starts.

Call (805) 499-0823

Or call (805) 499-0823. Monday to Friday, 9 to 5.

Request a site visit

Goes to the County Line office. The office calls you back. Privacy.

Discuss a Project